Modulation Drawing
Based on the packing list first the panels are shortlisted, which will become the major part of the designed panels. In the drawing based on the design and loading criteria’s. After all the shortlisted panels are consumed then the balance part is designed with the remaining panels of the inventory which will get used after modification.Finally, the remaining blanks are filled with new components.
Likewise, the drawing is completed and is forwarded to the design head for checking and review. Once the comments from the design head is implemented then the drawing is sent back for approval.
From the approved modulation drawing, an IPO list is created, which is sub-categorised in 3 units namely: -After the list is finalised then the re-usability percentage is calculated, and the same drawing is passed on if the re-usability percentage is more than 80% of the total inventory area.
Modulation drawing is prepared as per Aluminium formwork international standard scheme drawing. All the vertical formwork is shown in individual elevations, which makes the drawings easy to read, and even a labour foreman can understand the drawing and carry on erection on his own..